W-Industries has made its U.S.-engineered 38 kV metal-clad, air-insulated medium-voltage switchgear available for data centers, behind-the-meter power projects, and utilities, adding another supply option as 38 kV equipment demand ramps with large AI-driven builds. The lineup is tested to IEEE C37.20.2-2025 and has completed UL-witnessed testing at 1200 A and 2000 A configurations.
The switchgear is rated for 38 kV maximum at 50/60 Hz, with 1200 A and 2000 A continuous current ratings. Short-circuit ratings listed are 40 kA short-time withstand for 2 s, 104 kA peak for 10 power frequency cycles, 150 kV BIL, and 80 kV for 60 s power frequency withstand. W-Industries says UL witnessed the full test program covering the switchgear, its potential transformer (PT) truck, and its fuse truck, and that UL is issuing the certificate. Testing was witnessed at W-Industries and at KEMA Labs (Chalfont, Pennsylvania, and the Netherlands).
W-Industries lists several design details, including ground-up 38 kV PT and fuse-truck designs with hard-bussed PTs, automatic discharge during rack-out, and insulated rectangular bus bars intended to improve tracking resistance. The company also says customers can order custom configurations “within one footprint.” The design uses ABB ADVAC 38 kV draw-out circuit breakers and breaker cells.
For data center electrical teams, the immediate value here is straightforward: 38 kV distribution gear can be a schedule driver on greenfield campuses and private power builds, and adding a domestically assembled option could help reduce exposure to long lead times. But engineers will still want to scrutinize how the lineup fits their protection philosophy, lineup layout, and commissioning plan, especially around PT and fuse-truck configurations, relay integration, and arc-flash mitigation.
W-Industries says the switchgear works with “any relay platform,” allowing customers to keep their preferred protection and control equipment, and that its engineers can support surrounding electrical studies and settings work, including power system and arc flash studies, protective device coordination, relay settings, and IEC 61850 configuration.
“The mission now is to shave weeks off 38kV lead times,” said Todd Simmering, Senior Vice President, Electrification, at W-Industries. W-Industries also said 3000 A and 4000 A versions are in development, along with an outdoor NEMA 3R enclosure.
Source: W-Industries