MOU targets 0.75MW modular AI data center buildout in South Korea

GoodVision AI and ATTO Research have signed an MOU to jointly develop a network of supply chain-focused AI data centers in South Korea, with an initial joint commitment of at least $50 million. The effort targets phased buildouts near Seoul, Busan, and Daegu, pairing data center development and power sourcing with AI inference compute and “AI Factory” deployment capabilities.

The MOU sets a phased capacity plan: an initial build of 0.75 MW of AI Factory compute capacity, followed by a second phase targeting 5.5 MW by 2027. The longer-term goal is 40 MW of combined capacity across multiple sites.

For data center operators, the practical issue being called out here is schedule mismatch. The companies argue that enterprise customers can procure GPU servers in months, while traditional data center builds can take years, and they’re aiming to deliver modular AI data centers on timelines aligned with GPU procurement cycles. That approach can reduce stranded GPU capex and stalled AI deployments, but execution will hinge on site readiness, power availability, and how “modular” translates into real commissioning timelines.

Under the agreement, ATTO Research is responsible for site and power infrastructure resources, power sourcing, network integration, and local development in South Korea. GoodVision AI is contributing AI inference computing expertise, AI Factory deployment capabilities, intelligent compute scheduling, and edge AI network expansion.

Davy Wang, CEO of GoodVision AI, said, “Demand for purpose-built compute capacity is outpacing what traditional data center development can deliver.” Dr. Jae Woong Chung, CEO of ATTO Research, said, “New data center space takes years. GPU servers arrive in months.”

Source: Business Wire

Yokogawa — below-posts ()

Get Data Center Engineering News In Your Inbox:

By subscribing, you agree to our Privacy Policy and Terms of Use. You can unsubscribe at any time.

Sponsored: Infineon at OCP 2026: Exclusive Content Hub. Executive interviews, technical documents, reference designs, and live expert panel. Unlock the hub.
Chroma — tower

Popular Posts:

Screenshot
Solid-state transformer converts 13.8 kV AC to 800 VDC, Enphase says
data-center-cooling-tower-basin
Data center coatings and fireproofing: Earlier supplier collaboration could save build teams millions
image-10
Delta debuts 2.5 MW 800 VDC in-row liquid-to-liquid CDU at SC26
Mission-critical data center cooling webinar
Webinar: Gaskets for mission-critical data center power and cooling
Dewalt-31
The data center critical path runs through the slab, and DEWALT wants a robot on it

Share Your Data Center Engineering News

Do you have a new product announcement, webinar, whitepaper, or article topic? 

TDK — tower ()

Get Data Center Engineering News In Your Inbox:

By subscribing, you agree to our Privacy Policy and Terms of Use. You can unsubscribe at any time.

Yokogawa — leaderboard ()